The final two stages in the assembly of the windows and doors are painting the frames and installing glass – a process known as glazing. The racks on which the windows and doors are moved all have the same configuration with each holding 5 units per rack. After painting is completed, the painters move the frames into an automatic glazing workstation at the rate of one rack every 1 5 minutes. However, the painting process often outpaces glazing leaving an excessive number of painted units awaiting glazing. To evaluate how a “ pull ” system could improve the painting and glazing processes, answer the following questions: A . How many racks of windows and doors should move between painting and glazing if 2 9 0 units are to be completed each 8 - hour shift? Assume that the safety stock policy variable α is 0 . 1 5 and the average waiting / handling time is 9 minutes per rack. B . What is the significance of determining the correct number of racks ( or Kanbans ) between the paint machine and glazing machine? In other words, how does it affect Olde World ’ s operational competitiveness? fill in excel: Daily Expected Demand Quantity in Standard Container Container Waiting Time ( days ) Processing Time ( days ) Policy Variable

Question:

The final two stages in the assembly of the windows and doors are painting the frames and installing glass – a process known as glazing. The racks on which the windows and doors are moved all have the same configuration with each holding 5 units per rack. After painting is completed, the painters move the frames into an automatic glazing workstation at the rate of one rack every 1 5 minutes. However, the painting process often outpaces glazing leaving an excessive number of painted units awaiting glazing. To evaluate how a “ pull ” system could improve the painting and glazing processes, answer the following questions: A . How many racks of windows and doors should move between painting and glazing if 2 9 0 units are to be completed each 8 - hour shift? Assume that the safety stock policy variable α is 0 . 1 5 and the average waiting / handling time is 9 minutes per rack. B . What is the significance of determining the correct number of racks ( or Kanbans ) between the paint machine and glazing machine? In other words, how does it affect Olde World ’ s operational competitiveness? fill in excel: Daily Expected Demand Quantity in Standard Container Container Waiting Time ( days ) Processing Time ( days ) Policy Variable

This is AI generated Response.
Asked by: pr
Created at: 2025-05-26 18:16:23

Final Answer:

Rendered Raw Text
Did you like this answer?
Let's break down the problem step by step, then show how to fill in the Excel fields: ### **A. Calculating Number of Racks (Kanbans) Needed Between Painting and Glazing** #### **Step 1: Calculate Daily Expected Demand** - **Units to be completed per shift:** 290 units - **Shift duration:** 8 hours (480 minutes) - **Units per rack:** 5 - **Racks needed per shift:** \[ \text{Racks per shift} = \frac{290\ \text{units}}{5\ \text{units/rack}} = 58\ \text{racks} \] #### **Step 2: Calculate Container Waiting Time (days)** - **Average waiting/handling time per rack:** 9 minutes - **1 day = 480 minutes (8-hour shift)** - **Waiting time in days:** \[ \text{Waiting Time (days)} = \frac{9\ \text{minutes}}{480\ \text{minutes/day}} = 0.01875 \] #### **Step 3: Calculate Processing Time (days)** - **Glazing rate:** 1 rack every 15 minutes - **Time to process 1 rack:** 15 minutes - **Processing time in days:** \[ \text{Processing Time (days)} = \frac{15\ \text{minutes}}{480\ \text{minutes/day}} = 0.03125 \] #### **Step 4: Policy Variable (α)** - **Given:** α = 0.15 #### **Step 5: Kanban (Rack) Calculation Formula** The **Kanban formula** is: \[ \text{Number of Kanbans} = \left( \frac{\text{Daily Demand} \times (\text{Waiting Time} + \text{Processing Time})}{\text{Units per Rack}} \right) \times (1 + \alpha) \] Plug in the numbers: - **Daily Demand:** 290 units - **Waiting Time:** 0.01875 days - **Processing Time:** 0.03125 days - **Units per rack:** 5 - **Policy variable:** 0.15 \[ \text{Number of Kanbans} = \left( \frac{290 \times (0.01875 + 0.03125)}{5} \right) \times (1 + 0.15) \] \[ = \left( \frac{290 \times 0.05}{5} \right) \times 1.15 \] \[ = \left( \frac{14.5}{5} \right) \times 1.15 \] \[ = 2.9 \times 1.15 = 3.335 \] **So, you would need at least 4 racks (since you can't have a fraction of a rack) between painting and glazing.** --- ### **B. Significance of Correct Number of Racks (Kanbans)** - Ensures **smooth material flow** without overproduction or excessive waiting. - Too few racks = **starvation** at glazing, lost production time. - Too many racks = **excess WIP inventory**, higher costs, and less responsiveness. - Correct Kanban count **optimizes inventory, reduces lead time, and improves responsiveness to customer demand.** - **Operational competitiveness** is enhanced by minimizing waste, improving throughput, and reducing costs. --- ### **Excel Table Fill-In** | | Value | |--------------------------|----------------------| | Daily Expected Demand | 290 | | Quantity in Standard Container | 5 | | Container Waiting Time (days) | 0.01875 | | Processing Time (days) | 0.03125 | | Policy Variable | 0.15 | --- ### **Summary Table for Excel** | Field | Value | |-------------------------------|------------| | Daily Expected Demand | 290 | | Quantity in Standard Container| 5 | | Container Waiting Time (days) | 0.01875 | | Processing Time (days) | 0.03125 | | Policy Variable | 0.15 | | **Number of Kanbans/Racks** | **4** | You can use this table as your Excel input. If you need an Excel formula, you can use: ```excel =ROUNDUP(((290*(0.01875+0.03125))/5)*(1+0.15), 0) ``` This will yield **4 Kanbans/Racks**. --- If you need a template or the calculation steps in Excel, let me know!

Question:

i need detailed calculations of each part along with the final Answer

This is AI generated Response.
Asked by: pr
Created at: 2025-05-26 19:48:31

Final Answer:

Rendered Raw Text
Did you like this answer?
Certainly! Here's a detailed breakdown of each part of the calculation, including all steps and reasoning, followed by the final answer. --- ### **Part A: Calculating the Number of Racks (Kanbans) Needed** #### **1. Determine the Daily Demand in Units** - **Units to be completed per shift:** 290 units - **Shift length:** 8 hours = 480 minutes - **Units per rack:** 5 units **Racks needed per shift:** \[ \text{Racks per shift} = \frac{\text{Units per shift}}{\text{Units per rack}} = \frac{290}{5} = 58\ \text{racks} \] This means each shift requires moving 58 racks from painting to glazing. --- #### **2. Calculate the Container Waiting Time (in days)** - **Average waiting/handling time per rack:** 9 minutes - **Total minutes in a day (shift duration):** 8 hours = 480 minutes **Waiting time in days:** \[ \text{Waiting Time} = \frac{9\ \text{minutes}}{480\ \text{minutes/day}} = 0.01875\ \text{days} \] This represents the average time a rack spends waiting before being processed in days. --- #### **3. Calculate the Processing Time per Rack (in days)** - **Processing rate:** 1 rack every 15 minutes **Processing time for one rack:** \[ \text{Processing Time} = \frac{15\ \text{minutes}}{480\ \text{minutes/day}} = 0.03125\ \text{days} \] --- #### **4. Incorporate the Policy Variable (\(\alpha\))** Given: \[ \alpha = 0.15 \] This accounts for safety stock or buffer (to prevent stockouts). --- #### **5. Calculate the Number of Kanbans (Racks) Needed** The general **Kanban formula** is: \[ \boxed{ \text{Number of Kanbans} = \left( \frac{\text{Daily Demand} \times (\text{Waiting Time} + \text{Processing Time})}{\text{Units per Rack}} \right) \times (1 + \alpha) } \] **Plugging in the values:** - Daily demand (units): **290** - Waiting time: **0.01875 days** - Processing time: **0.03125 days** - Units per rack: **5** - Safety factor: **1 + 0.15 = 1.15** **Calculation:** \[ \text{Number of Kanbans} = \left( \frac{290 \times (0.01875 + 0.03125)}{5} \right) \times 1.15 \] \[ = \left( \frac{290 \times 0.05}{5} \right) \times 1.15 \] \[ = \left( \frac{14.5}{5} \right) \times 1.15 \] \[ = 2.9 \times 1.15 = 3.335 \] Since the number of racks must be a whole number, **round up** to **4** racks. --- ### **Final Result for Part A:** **Number of racks (Kanbans) needed between painting and glazing:** \[ \boxed{\textbf{4 racks}} \] --- ### **Part B: Significance of Correct Number of Racks (Kanbans)** - **Operational Flow:** Correct Kanban size ensures smooth flow of materials. Too few racks cause delays (starvation at the glazing station), reducing throughput. - **Inventory Management:** Too many racks increase Work-In-Progress (WIP), leading to higher storage costs and potential waste. - **Responsiveness:** Proper Kanban levels allow the system to respond quickly to demand changes, improving flexibility. - **Cost Efficiency:** Minimizing excess WIP reduces inventory holding costs and improves cash flow. - **Competitive Advantage:** Well-calibrated Kanban systems help Olde World maintain high efficiency, reduce lead times, and lower costs, thus enhancing its competitiveness. --- ### **Excel Data Summary** | Field | Calculation / Value | |------------------------------|--------------------------------------------| | Daily Expected Demand | **290 units** | | Quantity per Standard Container | **5 units** | | Container Waiting Time (days) | **=9/480 = 0.01875** | | Processing Time (days) | **=15/480 = 0.03125** | | Policy Variable (\(\alpha\)) | **0.15** | | **Number of Kanbans (rounded up)** | **4** | --- ### **Excel Formula for Number of Kanbans:** ```excel =ROUNDUP(((290 * (0.01875 + 0.03125)) / 5) * (1 + 0.15), 0) ``` This formula yields **4** as the required number of racks (Kanbans). --- **Summary:** - **Part A:** 4 racks - **Part B:** Proper Kanban sizing ensures smooth operations, reduces costs, and enhances Olde World’s competitiveness. If you'd like, I can prepare a detailed Excel sheet template with these calculations!

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.