Give step-by-step solution with explanation and final answer:Problem 20-22 (Algo) Annual demand for a product is 8,320 units; weekly demand is 160 units with a standard deviation of 60 units. The cost of placing an order is $145, and the time from ordering to receipt is four weeks. The annual inventory carrying cost is $0.85 per unit. a. To provide a 90 percent service probability, what must the reorder point be? Note: Use Excel's NORMSINV() function to find the correct critical value for the given a-level. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to the nearest whole number. b. Suppose the production manager is told to reduce the safety stock of this item by 90 units. If this is done, what will the new service probability be? Note: Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Round your answer to the nearest whole number.

Question:

Give step-by-step solution with explanation and final answer:Uploaded ImageProblem 20-22 (Algo) Annual demand for a product is 8,320 units; weekly demand is 160 units with a standard deviation of 60 units. The cost of placing an order is $145, and the time from ordering to receipt is four weeks. The annual inventory carrying cost is $0.85 per unit. a. To provide a 90 percent service probability, what must the reorder point be? Note: Use Excel's NORMSINV() function to find the correct critical value for the given a-level. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to the nearest whole number. b. Suppose the production manager is told to reduce the safety stock of this item by 90 units. If this is done, what will the new service probability be? Note: Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Round your answer to the nearest whole number.

This is AI generated Response.
Asked by: gvr
Created at: 2025-07-30 01:14:09

Final Answer:

Rendered Raw Text
Did you like this answer?
Let's solve each part step by step: ### **Given Data** - **Annual demand (D)** = 8,320 units - **Weekly demand** = 160 units - **Std dev of weekly demand (σ_w)** = 60 units - **Lead time (L)** = 4 weeks --- ### **a. To provide a 90% service probability, what must the reorder point be?** #### 1. **Find the mean demand during lead time (μ_L):** \[ \mu_L = \text{Weekly demand} \times \text{Lead time} = 160 \times 4 = 640 \text{ units} \] #### 2. **Calculate the standard deviation during lead time (σ_L):** \[ \sigma_L = \sqrt{L} \times \sigma_w = \sqrt{4} \times 60 = 2 \times 60 = 120 \text{ units} \] #### 3. **Find the z-value for 90% service probability:** - For a 90% service probability, the alpha level is 0.90. - Using Excel's **NORM.S.INV(0.90)** or a z-table: \[ z = NORM.S.INV(0.90) \approx 1.28 \] *(Rounded to 2 decimal places as requested)* #### 4. **Calculate the reorder point:** \[ \text{Reorder point} = \mu_L + z \cdot \sigma_L = 640 + 1.28 \times 120 = 640 + 153.6 = 793.6 \] - **Round to the nearest whole number:** \[ \text{Reorder point} = \boxed{794} \text{ units} \] --- ### **b. If safety stock is reduced by 90 units, what is the new service probability?** #### 1. **Find the new reorder point:** - Original reorder point = 794 units - New reorder point = 794 - 90 = 704 units #### 2. **Find the new z-value:** \[ z = \frac{\text{New reorder point} - \mu_L}{\sigma_L} = \frac{704 - 640}{120} = \frac{64}{120} \approx 0.53 \] #### 3. **Find the new service probability:** - Use Excel's **NORM.S.DIST(0.53, TRUE)** or a z-table: \[ \text{Service probability} = NORM.S.DIST(0.53, TRUE) \approx 0.7019 \] - Convert to percentage and round to the nearest whole number: \[ \text{Service probability} = 70\% \] --- ## **Final Answers** **a. Reorder point:** \[ \boxed{794 \text{ units}} \] **b. Service probability:** \[ \boxed{70\%} \] Let me know if you'd like to see the calculations in Excel as well!

Question:

I NEED DTEP BY STEP DETAILED CALCULATIONS OF EACH PART ALONG WITH THE FINAL ANSWER

This is AI generated Response.
Asked by: gvr
Created at: 2025-07-30 01:15:30

Final Answer:

Rendered Raw Text
Did you like this answer?
Certainly! Let's go through each part step-by-step with detailed calculations, explanations, and final answers. --- ## **Given Data Recap:** | Parameter | Value | |-------------|---------| | Annual demand \(D\) | 8,320 units | | Weekly demand | 160 units | | Standard deviation of weekly demand \(\sigma_w\) | 60 units | | Lead time \(L\) | 4 weeks | | Inventory carrying cost per unit | $0.85 (not needed for this part) | | Ordering cost | $145 (not needed here) | --- ## **Part a: Determine Reorder Point for 90% Service Level** ### **Step 1: Find the mean demand during the lead time \(\mu_L\)** - The mean demand during lead time = weekly demand \(\times\) lead time \[ \boxed{ \mu_L = 160 \times 4 = 640 \text{ units} } \] **Explanation:** This is the expected number of units consumed during the 4-week lead time. --- ### **Step 2: Find the standard deviation of demand during lead time \(\sigma_L\)** - Since demand variances for independent periods add, the standard deviation during lead time is: \[ \sigma_L = \sqrt{L} \times \sigma_w \] - Calculate: \[ \sigma_L = \sqrt{4} \times 60 = 2 \times 60 = 120 \text{ units} \] **Explanation:** The variability during the lead time accounts for weekly demand fluctuations over 4 weeks. --- ### **Step 3: Find the z-value for 90% service probability** - For a service probability of 90%, the critical z-value from the standard normal distribution: \[ z = \text{NORM.S.INV}(0.90) \] - Using Excel: ```excel =NORMSINV(0.90) ``` - Approximate value: \[ z \approx 1.28 \] *(Rounded to 2 decimal places as instructed)* --- ### **Step 4: Calculate the Reorder Point (ROP)** \[ \text{ROP} = \mu_L + z \times \sigma_L \] Substitute the values: \[ \text{ROP} = 640 + 1.28 \times 120 = 640 + 153.6 = 793.6 \] - Round to the nearest whole number: \[ \boxed{ \textbf{Reorder Point} = \boxed{794 \text{ units}} } \] --- ## **Part b: Effect of reducing safety stock by 90 units on service probability** ### **Step 1: Find the new reorder point** - The safety stock is essentially the safety component: \[ \text{Original safety stock} = \text{ROP} - \mu_L = 794 - 640 = 154 \text{ units} \] - Reduced safety stock: \[ \text{New safety stock} = 154 - 90 = 64 \text{ units} \] - New reorder point: \[ \text{New ROP} = \mu_L + \text{new safety stock} = 640 + 64 = 704 \text{ units} \] Alternatively, directly subtract 90 units from the old ROP: \[ 794 - 90 = 704 \text{ units} \] --- ### **Step 2: Compute the new z-value** \[ z = \frac{\text{New ROP} - \mu_L}{\sigma_L} = \frac{704 - 640}{120} = \frac{64}{120} \approx 0.5333 \] ### **Step 3: Find the new service probability** - Using Excel: ```excel =NORM.S.DIST(0.5333, TRUE) ``` - Approximate value: \[ \text{Service probability} \approx 0.702 \] - Convert to percentage: \[ 70.2\% \] - Rounded to the nearest whole number: \[ \boxed{70\%} \] --- ## **Final Summary:** | Part | Answer | Explanation | |---------|--------|-------------| | **a** | **794 units** | Reorder point to maintain a 90% service level considering demand variability during lead time. | | **b** | **70%** | Service probability after safety stock reduction by 90 units. | --- Feel free to ask for further clarifications!

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.