Give step-by-step solution with explanation and final answer:Design a scpic tank (0 treat wastewstr from an institute having | number of users 50 person for specified region. Consider the specific water consumption is 100 fpcd and destudging period 1s 2 years.
Question:
Give step-by-step solution with explanation and final answer:
Design a scpic tank (0 treat wastewstr from an institute having |
number of users 50 person for specified region. Consider the
specific water consumption is 100 fpcd and destudging period 1s
2 years.
This is AI generated Response.
Asked by: VARRI APPARAO
Created at: 2025-10-03 11:03:59
Asked by: VARRI APPARAO
Created at: 2025-10-03 11:03:59
Final Answer:
Rendered
Raw Text
Did you like this answer?
## Problem Restatement**Design a septic tank to treat wastewater from an institute with:**
- Number of users = 50 persons
- Water consumption = 100 liters per capita per day (lpcd)
- Desludging period = 2 years
---
## Step-by-Step Solution
### **Step 1: Calculate Total Wastewater Generated per Day**
\[
\text{Total wastewater/day} = \text{Number of users} \times \text{Water consumption}
\]
\[
= 50 \times 100 = 500 \text{ liters/day}
\]
---
### **Step 2: Determine Retention Time**
**Standard retention time for septic tank:**
- Domestic sewage: **24 hours** (1 day)
---
### **Step 3: Calculate Volume Required for Liquid**
\[
\text{Volume for liquid} = \text{Total wastewater/day} \times \text{Retention time}
\]
\[
= 500 \text{ liters} \times 1 \text{ day} = 500 \text{ liters}
\]
\[
= 5. \text{ m}^3 \qquad (1 \text{ m}^3 = 100 \text{ liters})
\]
---
### **Step 4: Calculate Sludge and Scum Accumulation**
#### **A. Sludge Accumulation**
- **Sludge production:** 30 liters/person/year (standard value)
- Over 2 years:
\[
\text{Total sludge} = 50 \times 30 \times 2 = 300 \text{ liters}
\]
\[
= 3. \text{ m}^3
\]
#### **B. Scum Accumulation**
- **Scum production:** 30 liters/person/year (approximate, similar to sludge)
\[
\text{Total scum} = 50 \times 30 \times 2 = 300 \text{ liters}
\]
\[
= 3. \text{ m}^3
\]
---
### **Step 5: Calculate Total Tank Volume**
\[
\text{Total volume required} = \text{Volume for liquid} + \text{Sludge} + \text{Scum}
\]
\[
= 5. + 3. + 3. = 11. \text{ m}^3
\]
**Add 10% freeboard (for safety):**
\[
\text{Freeboard} = .10 \times 11. = 1.1 \text{ m}^3
\]
\[
\text{Total volume} = 11. + 1.1 = 12.1 \text{ m}^3
\]
---
### **Step 6: Propose Septic Tank Dimensions**
A typical proportion for septic tanks is:
**Length : Width : Depth = 3 : 1 : 1.5**
Let width = \( w \)
Length = \( 3w \)
Depth = \( 1.5w \)
\[
\text{Volume} = \text{Length} \times \text{Width} \times \text{Depth}
\]
\[
12.1 = 3w \times w \times 1.5w = 4.5w^3
\]
\[
w^3 = \frac{12.1}{4.5} = 2.689
\]
\[
w = \sqrt[3]{2.689} \approx 1.39 \text{ m}
\]
So,
- **Width** = 1.39 m
- **Length** = 3 × 1.39 = **4.17 m**
- **Depth** = 1.5 × 1.39 = **2.09 m**
---
## **Final Answer**
### **Septic Tank Design Summary**
- **Capacity:** **12.1 m³**
- **Dimensions (approx.):**
- **Length:** 4.2 m
- **Width:** 1.4 m
- **Depth:** 2.1 m
- **Retention Time:** 24 hours
- **Desludging Period:** 2 years
---
### **Notes**
- Adjust dimensions as per site conditions.
- Provide inlet and outlet chambers, baffle walls, and manhole covers as per standard practice.