Give step-by-step solution with explanation and final answer:Design a scpic tank (0 treat wastewstr from an institute having | number of users 50 person for specified region. Consider the specific water consumption is 100 fpcd and destudging period 1s 2 years.

Question:

Give step-by-step solution with explanation and final answer:Uploaded ImageDesign a scpic tank (0 treat wastewstr from an institute having | number of users 50 person for specified region. Consider the specific water consumption is 100 fpcd and destudging period 1s 2 years.

This is AI generated Response.
Asked by: VARRI APPARAO
Created at: 2025-10-03 11:03:59

Final Answer:

Rendered Raw Text
Did you like this answer?
## Problem Restatement**Design a septic tank to treat wastewater from an institute with:** - Number of users = 50 persons - Water consumption = 100 liters per capita per day (lpcd) - Desludging period = 2 years --- ## Step-by-Step Solution ### **Step 1: Calculate Total Wastewater Generated per Day** \[ \text{Total wastewater/day} = \text{Number of users} \times \text{Water consumption} \] \[ = 50 \times 100 = 500 \text{ liters/day} \] --- ### **Step 2: Determine Retention Time** **Standard retention time for septic tank:** - Domestic sewage: **24 hours** (1 day) --- ### **Step 3: Calculate Volume Required for Liquid** \[ \text{Volume for liquid} = \text{Total wastewater/day} \times \text{Retention time} \] \[ = 500 \text{ liters} \times 1 \text{ day} = 500 \text{ liters} \] \[ = 5. \text{ m}^3 \qquad (1 \text{ m}^3 = 100 \text{ liters}) \] --- ### **Step 4: Calculate Sludge and Scum Accumulation** #### **A. Sludge Accumulation** - **Sludge production:** 30 liters/person/year (standard value) - Over 2 years: \[ \text{Total sludge} = 50 \times 30 \times 2 = 300 \text{ liters} \] \[ = 3. \text{ m}^3 \] #### **B. Scum Accumulation** - **Scum production:** 30 liters/person/year (approximate, similar to sludge) \[ \text{Total scum} = 50 \times 30 \times 2 = 300 \text{ liters} \] \[ = 3. \text{ m}^3 \] --- ### **Step 5: Calculate Total Tank Volume** \[ \text{Total volume required} = \text{Volume for liquid} + \text{Sludge} + \text{Scum} \] \[ = 5. + 3. + 3. = 11. \text{ m}^3 \] **Add 10% freeboard (for safety):** \[ \text{Freeboard} = .10 \times 11. = 1.1 \text{ m}^3 \] \[ \text{Total volume} = 11. + 1.1 = 12.1 \text{ m}^3 \] --- ### **Step 6: Propose Septic Tank Dimensions** A typical proportion for septic tanks is: **Length : Width : Depth = 3 : 1 : 1.5** Let width = \( w \) Length = \( 3w \) Depth = \( 1.5w \) \[ \text{Volume} = \text{Length} \times \text{Width} \times \text{Depth} \] \[ 12.1 = 3w \times w \times 1.5w = 4.5w^3 \] \[ w^3 = \frac{12.1}{4.5} = 2.689 \] \[ w = \sqrt[3]{2.689} \approx 1.39 \text{ m} \] So, - **Width** = 1.39 m - **Length** = 3 × 1.39 = **4.17 m** - **Depth** = 1.5 × 1.39 = **2.09 m** --- ## **Final Answer** ### **Septic Tank Design Summary** - **Capacity:** **12.1 m³** - **Dimensions (approx.):** - **Length:** 4.2 m - **Width:** 1.4 m - **Depth:** 2.1 m - **Retention Time:** 24 hours - **Desludging Period:** 2 years --- ### **Notes** - Adjust dimensions as per site conditions. - Provide inlet and outlet chambers, baffle walls, and manhole covers as per standard practice.

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.