# Step-by-Step Solutions
---
## 1. Insurance for Vandalized Project Trailer
**Question:**
If a project trailer is vandalized, which of the following type of insurance would cover the claim?
### Choices:
- a. errors and omissions
- b. builder’s risk
- c. general liability
- d. property insurance
- e. None of these
### **Explanation:**
- **Errors and omissions:** Covers professional mistakes, not physical property damage.
- **Builder’s risk:** Covers buildings under construction, not equipment/trailers not being built.
- **General liability:** Covers injury or damage to others, not your own property.
- **Property insurance:** Covers damage to owned property, including vandalism.
### **Final Answer:**
**d. property insurance**
---
## 2. Cost Code Structure
**Question:**
Which of the following statements is true about a company's cost code structure?
### Choices:
- a. Organized alphabetically by item description
- b. Organized by sequence of installation
- c. Often organized by CSI division with adaptations
- d. Completely unique to each company
- e. None of these
### **Explanation:**
- Most companies use the **CSI (Construction Specifications Institute) division** as a base and adapt it to their needs.
### **Final Answer:**
**c. often organized by CSI division with adaptations by individual companies**
---
## 3. Best Contract Type When Scope is Defined but Quantities Are Not
**Question:**
Which of the following contract types is best used if the scope is well defined but not the quantities of material?
### Choices:
- a. lump sum
- b. unit price
- c. cost plus
- d. cost plus with GMP
- e. None of these
### **Explanation:**
- **Unit price** contracts are best when the type of work is known but exact quantities are not.
### **Final Answer:**
**b. unit price**
---
## 4. Historic Cost Index Calculation
### **Given Table:**
| Year | Amman | Irbid | Karak | Tafila |
|------|-------|-------|-------|--------|
| 2015 | 47. | 41. | 39.5 | 41. |
| 2012 | 41. | 36. | 34.5 | 34.5 |
### **Question:**
How much would a house that costs 500,000 JD in Karak in 2015 cost in 2012 if built in Tafila?
### **Step-by-Step Solution:**
- **Step 1:** Find the cost index for Karak in 2015: **39.5**
- **Step 2:** Find the cost index for Tafila in 2012: **34.5**
- **Step 3:** Use the formula:
\[
\text{Cost in 2012 Tafila} = \text{Cost in 2015 Karak} \times \left( \frac{\text{Index in 2012 Tafila}}{\text{Index in 2015 Karak}} \right)
\]
\[
\text{Cost in 2012 Tafila} = 500,000 \times \left( \frac{34.5}{39.5} \right)
\]
\[
= 500,000 \times .8734 = 436,684.81
\]
- **Step 4:** Match to the closest choice: **367,155 JD**, **628,947 JD**, **680,912 JD**, **889,685 JD**, **None of these**
### **Final Answer:**
**e. None of these**
---
## **Summary Table**
| # | Question Topic | Final Answer |
|---|-----------------------------|---------------------------------------------------|
| 1 | Vandalized trailer insurance| **d. property insurance** |
| 2 | Cost code structure | **c. often organized by CSI division...** |
| 3 | Contract type | **b. unit price** |
| 4 | Historic cost index | **e. None of these** |