Give step-by-step solution with explanation and final answer:1 17 OF 17 QUESTIONS REMAINING
activity times and slack times. Identify the critical path.
[1] Activity Predecessor Time/Duration (Days)
A Order Review None 2
B Order Standard Parts A 3
c Produce Standard Parts A 10
D Design Custom Parts A 13
E Software Development A 18
E Manufacture Custom cp 15
Hardware
G Assemble BF 10
H Test EG 5
Question:
Give step-by-step solution with explanation and final answer:1 17 OF 17 QUESTIONS REMAINING
activity times and slack times. Identify the critical path.
[1] Activity Predecessor Time/Duration (Days)
A Order Review None 2
B Order Standard Parts A 3
c Produce Standard Parts A 10
D Design Custom Parts A 13
E Software Development A 18
E Manufacture Custom cp 15
Hardware
G Assemble BF 10
H Test EG 5
This is AI generated Response.
Asked by: Veera manikanta
Created at: 2025-09-12 23:37:31
Final Answer:
RenderedRaw Text
Did you like this answer?
# Step-by-Step Solution: Critical Path Method (CPM)
Let's find the critical path, activity times, and slack times.
---
## **Step 1: List Activities, Durations, and Dependencies**
| ID | Activity | Predecessor | Duration (Days) |
|----|---------------------------|-------------|-----------------|
| A | Order Review | None | 2 |
| B | Order Standard Parts | A | 3 |
| C | Produce Standard Parts | A | 10 |
| D | Design Custom Parts | A | 13 |
| E | Software Development | A | 18 |
| F | Manufacture Custom Hardware | C, D | 15 |
| G | Assemble | B, F | 10 |
| H | Test | E, G | 5 |
---
## **Step 2: Draw the Network Diagram**
Let's represent the paths based on dependencies:
1. **A → B → G**
2. **A → C → F → G**
3. **A → D → F → G**
4. **A → E**
5. **E → H**
6. **G → H**
---
## **Step 3: Forward Pass (Earliest Start and Finish Times)**
### **Activity A**
- **ES = 0**
- **EF = ES + Duration = 0 + 2 = 2**
### **Activity B, C, D, E (all depend on A)**
- **ES = EF of A = 2**
- **B: EF = 2 + 3 = 5**
- **C: EF = 2 + 10 = 12**
- **D: EF = 2 + 13 = 15**
- **E: EF = 2 + 18 = 20**
### **Activity F (depends on C and D)**
- **ES = max(EF of C, EF of D) = max(12, 15) = 15**
- **EF = 15 + 15 = 30**
### **Activity G (depends on B and F)**
- **ES = max(EF of B, EF of F) = max(5, 30) = 30**
- **EF = 30 + 10 = 40**
### **Activity H (depends on E and G)**
- **ES = max(EF of E, EF of G) = max(20, 40) = 40**
- **EF = 40 + 5 = 45**
---
## **Step 4: Backward Pass (Latest Start and Finish Times)**
### **Activity H**
- **LF = EF = 45**
- **LS = LF - Duration = 45 - 5 = 40**
### **Activity G and E (predecessors to H)**
- **G: LF = LS of H = 40, LS = 40 - 10 = 30**
- **E: LF = LS of H = 40, LS = 40 - 18 = 22**
### **Activity F and B (predecessors to G)**
- **F: LF = LS of G = 30, LS = 30 - 15 = 15**
- **B: LF = LS of G = 30, LS = 30 - 3 = 27**
### **Activity C and D (predecessors to F)**
- **F depends on both C and D, so:**
- **C: LF = LS of F = 15, LS = 15 - 10 = 5**
- **D: LF = LS of F = 15, LS = 15 - 13 = 2**
### **Activity A (predecessor to B, C, D, E)**
- **A's LF = min(LS of B, C, D, E) = min(27, 5, 2, 22) = 2**
- **LS = 2 - 2 = 0**
---
## **Step 5: Calculate Slack for Each Activity**
- **Slack = LS - ES (or LF - EF)**
| ID | ES | EF | LS | LF | Slack |
|----|-----|-----|-----|-----|-------|
| A | 0 | 2 | 0 | 2 | 0 |
| B | 2 | 5 | 27 | 30 | 25 |
| C | 2 | 12 | 5 | 15 | 3 |
| D | 2 | 15 | 2 | 15 | 0 |
| E | 2 | 20 | 22 | 40 | 20 |
| F | 15 | 30 | 15 | 30 | 0 |
| G | 30 | 40 | 30 | 40 | 0 |
| H | 40 | 45 | 40 | 45 | 0 |
---
## **Step 6: Identify the Critical Path**
The critical path is the sequence of activities with **zero slack**:
**A → D → F → G → H**
- Duration: \(2 + 13 + 15 + 10 + 5 = 45\) days
---
## **Final Answers**
### **Critical Path:**
**A → D → F → G → H**
### **Project Duration:**
**45 days**
### **Slack Times:**
- **A, D, F, G, H:** 0 (critical path)
- **B:** 25
- **C:** 3
- **E:** 20
---
### **Summary Table**
| Activity | ES | EF | LS | LF | Slack | On Critical Path? |
|----------|----|----|----|----|-------|-------------------|
| A | 0 | 2 | 0 | 2 | 0 | Yes |
| B | 2 | 5 | 27 | 30 | 25 | No |
| C | 2 | 12 | 5 | 15 | 3 | No |
| D | 2 | 15 | 2 | 15 | 0 | Yes |
| E | 2 | 20 | 22 | 40 | 20 | No |
| F | 15 | 30 | 15 | 30 | 0 | Yes |
| G | 30 | 40 | 30 | 40 | 0 | Yes |
| H | 40 | 45 | 40 | 45 | 0 | Yes |
---
**If you need a visual diagram, let me know!**
VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.
Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.