Give step-by-step solution with explanation and final answer:[=p orm mre feb! 5 en Ce [— f—
Question:
Give step-by-step solution with explanation and final answer:
[=p
orm mre feb!
5 en
Ce
[—
f—
This is AI generated Response.
Asked by: yashwant sharma
Created at: 2025-07-15 22:34:12
Asked by: yashwant sharma
Created at: 2025-07-15 22:34:12
Final Answer:
Rendered
Raw Text
Did you like this answer?
Sure! Let's solve each part step by step. I'll first transcribe the text for clarity, then show the calculations and final answers.
---
### **Transcribed Problem:**
**Daleman Company produces helmets (Model H42).**
- Setup time: 2 days
- Production rate: 750 units/day
- Expected annual demand: 36,000 units
- Lead time: 8 days
**Customer order:** 12,000 helmets, but the stipulation is that the helmets be delivered within one week (7 days) after order is placed.
---
### **Required:**
#### **1. Calculate the optimal batch size for Model H42 using the EOQ model.**
**EOQ (Economic Order Quantity) for production =**
\[
Q^* = \sqrt{\frac{2DS}{H} \cdot \frac{P}{P-d}}
\]
Where:
- \( D = \) annual demand = 36,000 units
- \( S = \) setup cost (not given, but not needed for just batch size since only time and rates matter in this context)
- \( H = \) holding cost per unit per year (not given explicitly)
- \( P = \) production rate = 750 units/day
- \( d = \) demand rate = 36,000 units/year = 100 units/day
So:
\[
Q^* = \sqrt{\frac{2DS}{H} \cdot \frac{P}{P-d}}
\]
But since setup cost and holding cost are not given, let's use the formula for a production run:
\[
\text{Batch size} = \frac{\text{Daily demand} \times \text{Setup time}}{1 - \frac{\text{Daily demand}}{\text{Production rate}}}
\]
But typically, EOQ for production is:
\[
\text{Optimal Lot Size} = \sqrt{\frac{2DS}{H} \times \frac{P}{P-d}}
\]
Since S and H are not given, let's focus on the process time:
#### **2. Was Bateman’s response to the customer right? Would a lot size be time-indicated to produce the number of units wanted by the customer?**
**Production Rate** = 750 units/day
**Units needed** = 12,000
**Days to produce** = \( \frac{12,000}{750} = 16 \) days
**Required delivery time** = 7 days
**Conclusion:** No, it's not possible to produce 12,000 units in 7 days at 750 units/day.
#### **3. Do you agree or disagree with the manager's grumbling about Bateman's inventory policy?**
"Last week the order because we didn’t have sufficient inventory. We try to keep more units in inventory to deal with unexpected orders like these.”
**Agree/Disagree:** Agree.
**Reason:** If you don’t keep buffer (safety stock), you can’t meet large, sudden orders.
#### **4. How much additional inventory would have been needed to meet the customer’s requirement?**
**Customer wants** = 12,000 units **in 7 days**
**Current inventory:** Assume none, since they couldn’t fulfill.
**Additional inventory needed = Order quantity = 12,000 units**
#### **5. Is it common for the account demand to occur from just a few, very large orders during the year, as Daleman had to carry more inventory?**
**Yes** — For lumpy or irregular demand, companies keep higher safety stock.
#### **6. Lead time reduction:**
If setup time is reduced to 0.5 day and total lead time to 5 days, what is the batch size now? (Round to nearest whole number.)
**Production rate** = 750 units/day
**Total time to meet order** = 5 days
**Units produced in 5 days = 750 × 5 = 3,750 units**
But they need 12,000 units. So,
If setup time is reduced to 0.5 day, and total time is 5 days:
\[
\text{Units produced in 5 days} = 750 \times 5 = 3,750 \text{ units}
\]
But if the batch size is asked for the *production run*:
\[
\text{Batch size} = \text{Production rate} \times \text{Production time}
\]
(But for EOQ, more details would be needed.)
---
### **Summary Table of Answers:**
#### **1. Calculate the optimal batch size for Model H42 using the EOQ model.**
- **Optimal batch size:** N/A (not enough data to calculate EOQ without setup or holding cost)
#### **2. Was Bateman’s response correct?**
- **No.** It is not possible to produce 12,000 units in 7 days at 750 units/day.
#### **3. Do you agree with the manager’s grumbling?**
- **Agree.** Safety stock is needed for unexpected large orders.
#### **4. How much additional inventory would have been needed?**
- **12,000 units.**
#### **5. Is it common for this type of order pattern, and does it require more inventory?**
- **Yes.**
#### **6. If setup time is reduced to 0.5 day and lead time to 5 days, what is the batch size?**
- **3,750 units.**
---
**If you want more detail or have the setup/holding costs, I can calculate actual EOQ!**
📢 Instructions:
- Ask anything relatd to above question only.
- For new Question goto :
VIPSolutions