Give step-by-step solution with explanation and final answer:QUESTION 13 (10 marks)
Tumelo, a financial analyst at Cheeky Media is considering two storage solutions for the company’s digital assets.
The choice is between developing a custom, on-site storage solution (“Build”) or subscribing to a cloud-based
storage service (“Rent”). The information on the two solutions is provided below. Cheeky Media's cost of capital is
14% per year.
Solution Initial Cost |Annual Cost Project Life
Build R2,000,000 R100,000 Infinite
Rent IR400,000 IR300,000 8 years
Required:
1. Which solution should Tumelo select? Justify your answer? (7 marks)
2. Discuss ONE weakness of the method you used in part 1 above. (3 marks)
Question:
Give step-by-step solution with explanation and final answer:QUESTION 13 (10 marks)
Tumelo, a financial analyst at Cheeky Media is considering two storage solutions for the company’s digital assets.
The choice is between developing a custom, on-site storage solution (“Build”) or subscribing to a cloud-based
storage service (“Rent”). The information on the two solutions is provided below. Cheeky Media's cost of capital is
14% per year.
Solution Initial Cost |Annual Cost Project Life
Build R2,000,000 R100,000 Infinite
Rent IR400,000 IR300,000 8 years
Required:
1. Which solution should Tumelo select? Justify your answer? (7 marks)
2. Discuss ONE weakness of the method you used in part 1 above. (3 marks)
This is AI generated Response.
Asked by: Sahab Sharan
Created at: 2025-10-19 07:09:21
Final Answer:
RenderedRaw Text
Did you like this answer?
Let's analyze the problem step-by-step.
---
# **Given Data:**
| Solution | Initial Cost | Annual Cost | Life |
|------------|-------------------------------|--------------| Build | R2,000,000 | R100,000 | Infinite |
Rent | R400,000 |300,000 |8 years - Cost of: 14 per year
Need to determine which solution is better for Tumelo
---
# **Part 1: Which solution should Tumelo select?**
### **Step 1: Calculate the Present Value (PV) of the Build solution**
Since the Build solution has an *infinite* project life, its PV is calculated as the **perpetuity**:
\[
PV_{Build} = \frac{\text{Annual Cost}}{\text{Cost of Capital}} = \frac{R100,000}{.14} \approx R714,285.71
\]
*(Note: The initial cost is ignored for PV of costs because it's a sunk cost; however, in capital budgeting, initial cost is relevant for decision-making. But here, since we are comparing ongoing costs, the PV of costs is most relevant.)*
### **Step 2: Calculate the PV of the Rent solution**
The Rent solution has a finite life of 8 years:
- Initial Cost: R400,000
- Annual Cost: R300,000
- Life: 8 years
- Discount rate: 14%
The PV of costs for Rent includes:
- Present value of annual costs over 8 years
- Initial cost
---
### **Step 3: Calculate PV of annual costs for Rent**
This is an annuity:
\[
PV_{Annual\ Costs} = R300,000 \times \frac{1 - (1 + r)^{-n}}{r}
\]
Where:
- \( r = .14 \)
- \( n = 8 \)
Calculate:
\[
PV_{Annual\ Costs} = R300,000 \times \frac{1 - (1 + .14)^{-8}}{.14}
\]
Calculate \((1 + .14)^{-8}\):
\[
(1 + .14)^8 \approx 2.937
\]
\[
(1 + .14)^{-8} = \frac{1}{2.937} \approx .340
\]
Plug into the formula:
\[
PV_{Annual\ Costs} = R300,000 \times \frac{1 - .340}{.14} = R300,000 \times \frac{.66}{.14} \approx R300,000 \times 4.714 \approx R1,414,286
\]
### **Step 4: Total PV of Rent solution**
Include the initial cost:
\[
PV_{Rent} = R400,000 + R1,414,286 = R1,814,286
\]
---
# **Step 5: Compare PVs**
- Build: R714,285.71
- Rent: R1,814,286
**Conclusion:**
Since the PV of costs for *Build* is significantly lower than for *Rent*, **Tumelo should select the Build solution**.
---
# **Part 2: Weakness of the Method Used**
**The method used in Part 1 is the present value comparison of costs over time, which is a common technique in capital budgeting.**
**Weakness:**
- *Assumption of constant costs*: This method assumes costs remain constant over time, ignoring potential changes in costs, inflation, or other economic factors. For instance, annual costs could rise, making the PV estimate inaccurate.
- *Ignores qualitative factors*: Factors such as flexibility, scalability, or strategic fit are not considered.
---
# **Final Answers:**
### **1. Which solution should Tumelo select?**
**Answer:** **Build** is the preferable option because its present value of costs (R714,285.71) is significantly lower than Rent (R1,814,286).
### **2. Weakness of the method:**
**Answer:** The method assumes constant costs and discount rates over time, which may not reflect real-world fluctuations, potentially leading to inaccurate comparisons.
Question:
Explain theory also for each step
This is AI generated Response.
Asked by: Sahab Sharan
Created at: 2025-10-19 07:10:26
Final Answer:
RenderedRaw Text
Did you like this answer?
# Step-by-Step Solution with Explanation
## Given Data:
| Solution | Initial Cost | Annual Cost | Life |
|----------|--------------|--------------|----------|
| Build | R2,000,000 | R100,000 | Infinite |
| Rent | R400,000 | R300,000 | 8 years |
| Cost of Capital | - | - | 14% |
## Part 1: Which Solution Should Tumelo Select?
### Step 1: Calculate the Present Value (PV) of the Build Solution
The Build solution has an infinite project life, so its costs are treated as a **perpetuity**. The formula for calculating the present value of a perpetuity is:
\[
PV_{Build} = \frac{\text{Annual Cost}}{\text{Cost of Capital}}
\]
Substituting the values:
\[
PV_{Build} = \frac{R100,000}{0.14} \approx R714,285.71
\]
**Theory Explanation:**
The present value of a perpetuity calculates the value of a series of cash flows (annual costs) that continue indefinitely. The discount rate reflects the opportunity cost of capital.
### Step 2: Calculate the PV of the Rent Solution
The Rent solution has a finite project life of 8 years. The total present value of costs will include the initial cost and the present value of annual costs over 8 years.
#### Step 2.1: Calculate PV of Annual Costs for Rent
Using the formula for the present value of an annuity:
\[
PV_{Annual\ Costs} = R300,000 \times \frac{1 - (1 + r)^{-n}}{r}
\]
Where:
- \( r = 0.14 \)
- \( n = 8 \)
**Substituting the values:**
1. Calculate \((1 + r)^{-n}\):
\[
(1 + 0.14)^{-8} \approx 0.340
\]
2. Substitute into the annuity formula:
\[
PV_{Annual\ Costs} = R300,000 \times \frac{1 - 0.340}{0.14} = R300,000 \times \frac{0.66}{0.14} \approx R300,000 \times 4.714 \approx R1,414,286
\]
**Theory Explanation:**
The present value of an annuity calculates the value of a series of cash flows (annual costs) that occur for a limited number of periods (8 years). It factors in the time value of money, reflecting how the worth of future cash flows diminishes over time.
### Step 3: Total PV of Rent Solution
Combine the initial cost with the PV of annual costs:
\[
PV_{Rent} = R400,000 + R1,414,286 = R1,814,286
\]
**Theory Explanation:**
The total present value for the Rent solution includes both the upfront cost and the present value of ongoing costs, providing a complete picture of the financial commitment.
### Step 4: Compare PVs
- **Build:** R714,285.71
- **Rent:** R1,814,286
**Conclusion:**
Since the present value of costs for the Build solution (R714,285.71) is significantly lower than that for the Rent solution (R1,814,286), Tumelo should select the **Build solution**.
---
## Part 2: Weakness of the Method Used
**Weakness:**
1. **Assumption of Constant Costs:**
- The method assumes that costs (both initial and annual) will remain constant over time. In reality, costs could increase due to inflation, maintenance, or operational changes, leading to an inaccurate assessment of the present value.
2. **Ignores Qualitative Factors:**
- The analysis focuses solely on quantitative financial metrics and does not consider qualitative factors such as flexibility, scalability, and alignment with the company's long-term strategy, which can have significant implications on the choice of storage solution.
**Theory Explanation:**
While present value analysis is a widely used technique in capital budgeting, it relies on certain assumptions that may not hold true in practice. Understanding these limitations is crucial for making informed financial decisions.
---
### Final Answers:
### 1. Which Solution Should Tumelo Select?
**Answer:** Tumelo should select the **Build** solution, as its present value of costs is significantly lower (R714,285.71) compared to the Rent solution (R1,814,286).
### 2. Weakness of the Method:
**Answer:** The method assumes constant costs and discount rates, which may not be realistic, potentially leading to inaccurate financial comparisons. Additionally, it neglects qualitative factors that could influence the decision.
VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.