explain step by stepA company manufactures a standard electrical component and operates 12 months a year. The product has steady demand, and raw materials are ordered in fixed batch quantities. All finished goods are shipped immediately after production. The company wants to reduce its inventory-related costs by using the Economic Order Quantity (EOQ) model. Raw materials are delivered 5 working days after placing an order. The company operates 24 working days per month. Below is the relevant data: Table: Operational Data Parameter Value Monthly Demand 8,000 units Annual Demand 96,000 units Unit Cost of Material 3400 Annual Holding Cost Rate 25% of unit cost Ordering Cost per Order 32,000 Lead Time 5 working days Working Days per Month 24 days (A) Use the EOQ formula to calculate the Economic Order Quantity. (Show the formula and all steps.) (B) Based on the EOQ, calculate: i) Number of orders placed per year ii) Total ordering cost per year © Find the following: i) Average inventory level ii) Total annual holding cost (D) Calculate the Reorder Point (ROP) assuming uniform daily demand. (E) Draw a flowchart with these steps in order: 1. Place Order 2. Supplier Delivers 3. Store Raw Materials 4. Produce Goods 5. Dispatch Finished Goods Use standard flowchart shapes and arrows to show the flow.

Question:

explain step by stepUploaded ImageUploaded ImageA company manufactures a standard electrical component and operates 12 months a year. The product has steady demand, and raw materials are ordered in fixed batch quantities. All finished goods are shipped immediately after production. The company wants to reduce its inventory-related costs by using the Economic Order Quantity (EOQ) model. Raw materials are delivered 5 working days after placing an order. The company operates 24 working days per month. Below is the relevant data: Table: Operational Data Parameter Value Monthly Demand 8,000 units Annual Demand 96,000 units Unit Cost of Material 3400 Annual Holding Cost Rate 25% of unit cost Ordering Cost per Order 32,000 Lead Time 5 working days Working Days per Month 24 days (A) Use the EOQ formula to calculate the Economic Order Quantity. (Show the formula and all steps.) (B) Based on the EOQ, calculate: i) Number of orders placed per year ii) Total ordering cost per year © Find the following: i) Average inventory level ii) Total annual holding cost (D) Calculate the Reorder Point (ROP) assuming uniform daily demand. (E) Draw a flowchart with these steps in order: 1. Place Order 2. Supplier Delivers 3. Store Raw Materials 4. Produce Goods 5. Dispatch Finished Goods Use standard flowchart shapes and arrows to show the flow.

This is AI generated Response.
Asked by: Test User 100135
Created at: 2025-05-14 21:49:19

Final Answer:

Rendered Raw Text
Did you like this answer?
Let's solve each part step by step using the data provided. --- ### **(A) Calculate Economic Order Quantity (EOQ)** **EOQ Formula:** \[ EOQ = \sqrt{\frac{2DS}{H}} \] Where: - \( D \) = Annual demand = **96,000 units** - \( S \) = Ordering cost per order = **₹2,000** - \( H \) = Annual holding cost per unit = Holding cost rate × Unit cost = **25% × ₹400 = ₹100** **Plug in the values:** \[ EOQ = \sqrt{\frac{2 \times 96,000 \times 2,000}{100}} \] \[ = \sqrt{\frac{384,000,000}{100}} \] \[ = \sqrt{3,840,000} \] \[ = 1,960 \text{ units (rounded to nearest unit)} \] --- ### **(B) Based on EOQ, Calculate** #### **i) Number of orders placed per year** \[ \text{No. of orders per year} = \frac{D}{EOQ} = \frac{96,000}{1,960} \approx 49 \text{ orders} \] #### **ii) Total ordering cost per year** \[ \text{Total ordering cost} = \text{No. of orders} \times S = 49 \times ₹2,000 = ₹98,000 \] --- ### **(C) Find the following** #### **i) Average inventory level** \[ \text{Average inventory} = \frac{EOQ}{2} = \frac{1,960}{2} = 980 \text{ units} \] #### **ii) Total annual holding cost** \[ \text{Total holding cost} = \text{Average inventory} \times H = 980 \times ₹100 = ₹98,000 \] --- ### **(D) Calculate the Reorder Point (ROP)** \[ \text{Daily demand} = \frac{\text{Annual demand}}{\text{No. of working days per year}} \] \[ \text{Working days per year} = 24 \text{ days/month} \times 12 = 288 \text{ days} \] \[ \text{Daily demand} = \frac{96,000}{288} = 333.33 \text{ units/day} \] \[ \text{ROP} = \text{Daily demand} \times \text{Lead time} \] \[ \text{ROP} = 333.33 \times 5 = 1,667 \text{ units} \] --- ### **(E) Flowchart Steps** Here’s a simple textual representation of the flowchart steps: 1. **[Start]** 2. **[Process] Place Order** 3. **[Process] Supplier Delivers** 4. **[Process] Store Raw Materials** 5. **[Process] Produce Goods** 6. **[Process] Dispatch Finished Goods** 7. **[End]** You can draw this using flowchart shapes (rectangle for process, arrows for flow). --- ## **Summary Table** | Calculation | Value | |------------------------------- |-----------------| | EOQ | 1,960 units | | Number of Orders/Year | 49 | | Total Ordering Cost/Year | ₹98,000 | | Average Inventory Level | 980 units | | Total Annual Holding Cost | ₹98,000 | | Reorder Point (ROP) | 1,667 units | --- If you need the actual flowchart drawing, let me know and I can provide an image!

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.