3 . You have been asked to balance a flow shop assembly operation to achieve an output rate of 1 5 0 units per eight - hour day. Task times and precedence relationships are shown in the table below. Task Predecessor ( s ) Duration ( minutes ) A - - 1 . 4 B - - 0 . 8 C A , B 0 . 4 D - - 1 . 8 E - - 0 . 4 F C 3 . 0 G E , F 2 . 0 H D , G 1 . 2 ( a ) Draw the precedence diagram. ( b ) Determine the desired cycle time. ( c ) Determine the theoretical minimum number of stations needed. ( d ) Balance this line using the smallest processing time heuristic. ( e ) What is the efficiency of the line obtained in part d ? give all question answer and give final summary

Question:

3 . You have been asked to balance a flow shop assembly operation to achieve an output rate of 1 5 0 units per eight - hour day. Task times and precedence relationships are shown in the table below. Task Predecessor ( s ) Duration ( minutes ) A - - 1 . 4 B - - 0 . 8 C A , B 0 . 4 D - - 1 . 8 E - - 0 . 4 F C 3 . 0 G E , F 2 . 0 H D , G 1 . 2 ( a ) Draw the precedence diagram. ( b ) Determine the desired cycle time. ( c ) Determine the theoretical minimum number of stations needed. ( d ) Balance this line using the smallest processing time heuristic. ( e ) What is the efficiency of the line obtained in part d ? give all question answer and give final summary

This is AI generated Response.
Asked by: sreegeeth
Created at: 2025-11-19 09:25:14

Final Answer:

Rendered Raw Text
Did you like this answer?
# Flow Shop Assembly Line Balancing ## Given Data | Task | Predecessor(s) | Duration (minutes) | |------|----------------|-------------------| | A | - | 1.4 | | B | - | .8 | | C | A, B | .4 | | D | - | 1.8 | | E | - | .4 | | F | C | 3. | | G | E, F | 2. | | H | D, G | 1.2 | Required output rate: **150 units per 8-hour day** --- ## (a) Precedence Diagram ```mermaid graph TD A --> C B --> C C --> F E --> G F --> G D --> H G --> H ``` **Alt text:** A flow chart showing the tasks and their precedence relationships, as described in the table. --- ## (b) Desired Cycle Time 1. **Total time available per day:** \(8 \text{ hours} \times 60 = 480 \text{ minutes}\) 2. **Desired output:** \(150\) units per day 3. **Cycle time (\(CT\)):** \[ CT = \frac{\text{Total time available}}{\text{Required output}} = \frac{480}{150} = 3.2 \text{ minutes} \] --- ## (c) Theoretical Minimum Number of Stations 1. **Sum of all task times:** \[ 1.4 + .8 + .4 + 1.8 + .4 + 3. + 2. + 1.2 = 11. \text{ minutes} \] 2. **Theoretical minimum stations (\(N_{min}\)):** \[ N_{min} = \frac{\text{Total task time}}{\text{Cycle time}} = \frac{11.}{3.2} = 3.44 \] Round up: **4 stations** --- ## (d) Line Balancing (Smallest Processing Time Heuristic) **Heuristic:** Assign available tasks with the smallest duration as early as possible, respecting precedence. ### Step-by-Step Assignment #### **Station 1** (CT = 3.2 min) - **Available:** A (1.4), B (.8), D (1.8), E (.4) - Assign E (.4) → 2.8 min left - Assign B (.8) → 2. min left - Assign A (1.4) → .6 min left - Can't fit D (1.8) - **Total assigned:** E + B + A = .4 + .8 + 1.4 = **2.6 min** - Remaining: .6 min (cannot fit next available task) #### **Station 2** (CT = 3.2 min) - **Available:** D (1.8), C (.4) [A and B done] - Assign C (.4) → 2.8 min left - Assign D (1.8) → 1. min left - **Total assigned:** C + D = .4 + 1.8 = **2.2 min** - Remaining: 1. min #### **Station 3** (CT = 3.2 min) - **Available:** F (3.) [C done] - Assign F (3.) → .2 min left - **Total assigned:** F = **3. min** - Remaining: .2 min #### **Station 4** (CT = 3.2 min) - **Available:** G (2.) [E, F done] - Assign G (2.) → 1.2 min left - **Next:** H (1.2) [D, G done] - Assign H (1.2) → min left - **Total assigned:** G + H = 2. + 1.2 = **3.2 min** --- ### **Summary Table** | Station | Tasks | Total Time (min) | |---------|-----------------|------------------| | 1 | E, B, A | 2.6 | | 2 | C, D | 2.2 | | 3 | F | 3. | | 4 | G, H | 3.2 | --- ## (e) Line Efficiency \[ \text{Efficiency} = \frac{\text{Total task time}}{\text{Number of stations} \times \text{Cycle time}} \times 100\% \] \[ \text{Efficiency} = \frac{11.}{4 \times 3.2} \times 100\% = \frac{11.}{12.8} \times 100\% \approx 85.9\% \] --- # **Final Summary** - **Precedence diagram** is provided above (see mermaid graph). - **Desired cycle time:** 3.2 minutes per unit. - **Theoretical minimum stations:** 4. - **Balanced assignment (smallest processing time first):** - Station 1: E, B, A (2.6 min) - Station 2: C, D (2.2 min) - Station 3: F (3. min) - Station 4: G, H (3.2 min) - **Line efficiency:** ~85.9%

📢 Instructions:

  • Ask anything relatd to above question only.
  • For new Question goto :

Study Help, Fast Answers

VIPSolutions focuses on clear, step‑by‑step explanations so you can learn quickly. Whether you need an AI‑generated walkthrough or a short hint to get unstuck, each solution is organized for fast reading and easy review later.

Search similar questions, compare approaches, and bookmark the best answers for revision. Our goal is simple: quick, reliable study help that feels natural—not noisy.